"If You Dare Borrow, They Dare Lend": Discussing Data Center Financing, Power, Computing, and the...

Christina XuYixing XuAlex YehBruce Liu

Available power is becoming the gating asset for AI revenue, with Yixing Xu estimating 30–50% of this year’s planned data centers may use behind-the-meter generation.Bloom Energy could deliver power in three to six months, but supply, scale and maturity remain uncertain; meanwhile, delays may defer revenue after capital is committed.Operators must bridge 12–15-year leases against four- to six-year compute contracts, while regional flexibility and token sales help GMI Cloud monetize scarce capacity.